Weiss Construction served as the managing partner of the joint venture team that was awarded a $32 Million dollar contract with DWSD for the design/build delivery of a new water booster pumping station and reservoir facility located in Novi, Michigan.
Haggerty Road Pump Station
Haggerty Road Pump Station Novi, Michigan
Weiss Construction served as the managing partner for this award-winning project and self-performed all mechanical and process equipment work as well as all civil/site work, including excavation, yard piping, and structural concrete work. This fast track project was completed on time and with a net savings of $1.2 Million to the Owner.
- 12,000 sft booster pump station with a rated capacity of 70-mgd provided by three 700 HP VFD controlled line pumps and two 700 HP constant speed reservoir pumps
- A 10 million gallon prestressed, post-tensioned concrete above groundwater storage reservoir
- Approximately 1,000 linear feet of 36-inch and 42-inch yard piping comprised of concrete-encased AWWA C200 steel and AWWA C301 PCCP pipe
- Hot tap for connection to the existing 42-inch transmission main
- Electrical power distribution facilities and an Ovation based control system for remote and local monitoring and control of the facility.
- Over 3,000 lineal feet of 16-inch water main to provide an emergency supply of water of up to 28-mgd in the event of a water transmission main break between the Haggerty and Franklin Stations
- The seamless installation of a line pump and bypass chamber at the existing Rochester booster pump station